Key Takeaways

  1. San Joaquin County supervisors on Tuesday extended their data center moratorium in unincorporated areas by 10 months and 15 days.
  2. The original 45-day pause was adopted 5-0 on Oct. 6 as an urgency ordinance.
  3. No data center applications are pending in the county's unincorporated areas, according to Stocktonia.
  4. County staff are expected to deliver a full report on data center impacts to the board in June 2027.

San Joaquin County won't approve a new data center in its unincorporated areas for about another year.

The Board of Supervisors on Tuesday extended its moratorium on data center development for 10 months and 15 days, the Lodi News-Sentinel reported. Staff asked for the time to study what the facilities could mean for the county's environment and economy, and to hear from residents before anyone writes rules.

"We owe our residents answers before allowing development that could have negative consequences for our environment and economy," Board Chair Sonny Dhaliwal said.

No project is waiting on the outcome. Stocktonia reported that no companies have applications pending to build data centers in unincorporated parts of the county.

How the pause started

On Oct. 6, the supervisors voted 5-0 to adopt an urgency ordinance establishing a 45-day moratorium on new land-use approvals for data centers, Stocktonia reported. The ordinance covers general plan and zoning amendments, use permits, variances, parcel and final maps and building or grading permits that would allow a qualifying data center to go forward.

According to the agenda for that meeting, the moratorium doesn't apply to ordinary server rooms that are accessory to a permitted business. It also excludes telecommunication facilities, government emergency communication facilities, hospitals, schools and facilities owned or operated by public utilities.

At the time, Dhaliwal said the county "does not currently have specific standards to address the unique impacts of data centers, from noise and energy demands to emergency response and infrastructure capacity."

The board also told the Community Development Department to do an initial 10-day review of AI data centers. When staff presented their preliminary findings, they recommended keeping the pause in place.

A vote that waited a week

The extension needed a four-fifths majority of the board. Supervisors Steve Ding and Paul Canepa were absent when staff first brought it forward earlier this month, so the board put off a formal decision until the Nov. 17 meeting, Stocktonia reported.

"At the end of the day, we need to hear from the public," Supervisor Robert Rickman said.

Supervisor Mario Gardea put it this way: "Before we are put in a position to make a decision we need to be educated."

What staff will study

During the extension, staff will look at how other jurisdictions have handled data centers, do community outreach, assess potential demands on local resources and explore regulatory options, according to the News-Sentinel. The department will also work with a consultant on a more detailed analysis.

County staff said both traditional data centers and AI data centers can require large amounts of electricity and water. Staff told Stocktonia the fuller report will also look at narrower questions. One is whether a fire in the large battery storage units that might power some of the facilities could overwhelm firefighters in small rural fire districts.

The report is due to the board in June 2027.

The city of Stockton is working on the same question separately. Its City Council deleted data centers from its three-year economic development plan and is holding public listening sessions around the city, Stocktonia reported.

"We simply don't have enough information to make an informed decision on something that could have lasting consequences for our community," Community Development Department Director Jennifer Jolley said.